Updates for All Projects
-
View Project Details
Forest Hill Phase 4
St. Paul's (Ward 21)
Week of January 09, 2012
The civil construction portion of Project Hogg's Hollow Phase 4 is now complete. Toronto Hydro will now be proceeding with the electical phase of this project, by converting and energizing the new system in your neighbourhood. The electical phase of this project is expected to be completed by December 2012. The scope of work involves underground cable pulling, removal of overhead cables, removal of overhead transformers, and energization of padmounted transformers.
-
View Project Details
Strachan GO Transit
Trinity-Spadina (Ward 19)
Week of December 26, 2011
Following our initial letter dated July 19, 2011, Toronto Hydro-Electric System Limited (Toronto Hydro) has completed the civil construction as it relates to the Strachan GO Transit Georgetown expansion. Toronto Hydro anticipates to start the electrical phase of Project Strachan in early January 2012 with a completion date of December 2012, weather permitting.
The proposed work involves cable pulling, cable splicing and cable termination along Douro Street, Wellington Street West, Western Battery Road, Pirandello Street, East Liberty Street. No planned power interruptions will be required to complete this project.
-
View Project Details
Albion-Silverstone
Etobicoke North (Ward 1)
Week of December 26, 2011
Please be advised that Toronto Hydro-Electric System Limited (Toronto Hydro) has completed the civil construction for Project Albion-Silverstone and electrical construciton will begin in January 2012 and is tentatively scheduled to be completed in July 2012.
-
View Project Details
Carlton Church
Toronto Centre-Rosedale (Ward 27)
Week of December 26, 2011
Toronto Hydro would like to inform you that Project Carlton Church has been extended until Jan 13, 2012. The underground construction work is scheduled to take place from Jan 3 to Jan 13, 2012 on Church Street between Carlton Street and Granby Street.
-
View Project Details
Shalom Milkwood
Etobicoke North (Ward 1)
Week of December 26, 2011
Please be advised of the following changes to the planning of Project Shalom Milkwood. The construction is scheduled to commence in April 2012 and continue until November 2012. Our plan is to replace existing underground primary cables. As a result of this work, an above ground switchgear will be installed on Martin Grove Road.
-
View Project Details
Forest Hill Phase 5
St. Paul's (Ward 21)
Week of December 19, 2011
A total of 9 underground cable chambers will be installed within the City of Toronto’s roadways and public road allowance for Project Forest Hill Phase 5. The approximate locations planned for each cable chamber are identified by red squares on the associated map. Project Forest Hill Phase 5 will begin with the construction of these cable chambers. Road access and parking lanes will be used by our crews, which will reduce traffic to single lanes in each direction. Each cable chamber will take approximately 2 - 4 weeks (weather permitting) to be built, and will have a visible Toronto Hydro - Electric System Limited manhole lid, upon completion. Due to the road congestion we advise customers to allow additional time when travelling. We appreciate your cooperation and ask that customers exercise caution around construction areas.
-
View Project Details
Hogg's Hollow Phase 2
Don Valley West (Ward 25)
Week of December 12, 2011
The civil construction portion of Project Hogg's Hollow Phase 2 is now complete. Toronto Hydro will now be proceeding with the electical phase of this project, by converting and energizing the new system in your neighbourhood. The scope of work involves underground cable pulling, removal of overhead cables, removal of overhead transformers, and energization of padmounted transformers.
During the course of electrical work, we will be switching from the old to new power supply. You will likely experience intermittent power interruptions that are necessary for the safety of work crews. We will do our best to notify residents prior to these disruptions and to minimize any inconveniences. Please be advised that if you are not currently receiving underground service, or have not made prior arrangements during the civil phase, the services to your home will remain overhead through the usage of poles.
The electrical work is expected to commence in early January 2012, with completion expected by late March 2012, weather permitting. The affected streets are Plymbridge Road, May Tree Road, York Valley Crescent and Green Valley Road (please see map).
-
View Project Details
Lesmill
Don Valley West (Ward 25)
Week of December 12, 2011
Please note that the civil construction portion of Project Lesmill is now complete, with the electrical phase expected to commence in early January 2012.
-
View Project Details
Ripley
Parkdale-High Park (Ward 13)
Week of December 12, 2011
Toronto Hydro is pleased to note that the civil and electrical construction work associated with Project Ripley is now complete. Toronto Hydro would like to thank customers for their patience and cooperation throughout Project Ripley. All further questions about this project, or inquires about restoration can be directed to the Customer Operations team at 416-542-3366 or by email at capitalprojects@torontohydro.com. Please reference Project Ripley so we can better serve you.
-
View Project Details
Eglinton - Redpath
St. Paul's (Ward 22)
Week of December 12, 2011
Please be advised that the installation of new poles has been completed. Toronto Hydro will now be pulling wire and positioning equipment on these poles. We expect to have the old poles removed and the new system energized by May 2012. If you have any questions about Project Eglinton - Redpath or concerns regarding restoration after the old poles have been removed, please contact Toronto Hydro's powerUP office at 416 542 3366. We thank you again for your patience and cooperation.
