Aileen
Overview
- Ward: York South-Weston (Ward 12)
- Activity: Overhead Rebuild
- Timeline: October 2010 - January 2011
- Status: Completed
During this project crews will work along the streets bounded by: Aileen Ave. (north), Rogers Rd. (south), Silverhorn Ave. (west) and Blackhorn Ave. (east).
There are about 220 customers residing in this project area. The proposed work involves the installation of new poles and equipment within the public road allowance in front of or adjacent to your property. Construction started in late-October 2010, and will be finished in December 2010.
Customers living in this area may experience intermittent power interruptions that are necessary for the safety of work crews. We will do our best to notify residents prior to these disruptions. We will also endeavour to restore properties throughout the construction phase.
The following streets will be affected:
Aileen Ave
Blackthorn Ave
Failsworth Ave
Kenora Cr
Rogers Rd
Silverthorn Ave
Updates
- There are currently no updates for this project.