Updates for All Projects
-
View Project Details
Grand Marshall
Scarborough-Rouge River (Ward 42)
Week of May 07, 2012
The civil construction for Project Grand Marshall is scheduled to restart in June with completion expected by July 2012. The project was deferred as a result of the Ontario Energy Board’s review of Toronto Hydro’s capital budget. The electrical portion of Project Grand Marshall will occur as scheduling and funding permits.
-
View Project Details
Ingleton Phase A
Scarborough-Rouge River (Ward 41)
Week of May 07, 2012
The civil construction for Project Ingleton Phase A is scheduled to restart in June with completion expected by July 2012. The project was deferred as a result of the Ontario Energy Board’s review of Toronto Hydro’s capital budget. The electrical portion of Project Ingleton Phase A will occur as scheduling and funding permits.
-
View Project Details
Albion-Silverstone
Etobicoke North (Ward 1)
Week of May 07, 2012
The civil construction for Project Albion Silverstone was completed in 2010 and 2011. Toronto Hydro will now return to complete the electrical upgrade. Electrical work is expected to begin early May 2012 with an anticipated completion by December 2012, as weather, scheduling and funding permits.
-
View Project Details
Forest Hill Phase 4
St. Paul's (Ward 21)
Week of April 30, 2012
The civil construction for Project Forest Hill Phase 4 was completed in 2010 and 2011. Toronto Hydro will now return to complete the electrical upgrade. Electrical work is expected to begin early May 2012 with an anticipated completion by December 2012.
-
View Project Details
Forest Hill Phase 5
St. Paul's (Ward 21)
Week of April 30, 2012
The civil construction for Project Forest Hill Phase 5 is scheduled to restart in early May 2012 with completion expected by January 2013. The project was deferred as a result of the Ontario Energy Board’s review of Toronto Hydro’s capital budget.
If you received a letter indicating that "an underground cable chamber with a visible lid will be installed within the City of Toronto's roadway on your street", please see map for marked cable chamber locations near you.
-
View Project Details
Harrison Garden
Willowdale (Ward 23)
Week of April 23, 2012
The civil construction for Project Harrison Garden is scheduled to restart in mid May 2012 with completion by mid June 2012. The project was deferred as a result of the Ontario Energy Board’s review of Toronto Hydro’s capital budget.
-
View Project Details
Hupfield Phase 1
Scarborough-Rouge River (Ward 42)
Week of April 23, 2012
The civil construction for Project Hupfield Phase 1 is scheduled to restart in mid April 2012 with completion by mid July 2012. The project was deferred as a result of the Ontario Energy Board’s review of Toronto Hydro’s capital budget.
-
View Project Details
Hupfield Phase 2
Scarborough-Rouge River (Ward 42)
Week of April 23, 2012
The civil construction for Project Hupfield Phase 2 is scheduled to restart in early May 2012 with completion by the end of June 2012. The project was deferred as a result of the Ontario Energy Board’s review of Toronto Hydro’s capital budget.
-
View Project Details
Empringham
Scarborough-Rouge River (Ward 42)
Week of April 23, 2012
The civil construction for Project Empringham is scheduled to restart in early May 2012 with completion by mid July 2012. The project was deferred as a result of the Ontario Energy Board’s review of Toronto Hydro’s capital budget.
-
View Project Details
Pennyhill Phase 1
Scarborough-Rouge River (Ward 42)
Week of April 23, 2012
The civil construction for Project Pennyhill is scheduled to restart in early May 2012 with completion by the end of June 2012. The project was deferred as a result of the Ontario Energy Board’s review of Toronto Hydro’s capital budget.